The various parts of The Falkirk Wheel were all constructed and assembled, like one giant toy building set, at Butterley Engineering's Steelworks in Derbyshire, some 400 km from Falkirk. A team there carefully assembled the 1,200 tonnes of steel, painstakingly fitting the pieces together to an accuracy of just 10 mm to ensure a perfect final fit. In the summer of 2001, the structure was then dismantled and transported on 35 lorries to Falkirk, before all being bolted back together again on the ground, and finally lifted into position in five large sections by crane. The Wheel would need to withstand immense and constantly changing stresses as it rotated, so to make the structure more robust, the steel sections were bolted rather than welded together. Over 45,000 bolt holes were matched with their bolts, and each bolt was hand-tightened.
The various parts of The Falkirk Wheel were all constructed and assembled, like one giant toy building set, at Butterley Engineering's Steelworks in Derbyshire, some 400 km from Falkirk. A team there carefully assembled the 1, 200 tonnes of steel, painstakingly fitting the pieces together to an accuracy of just 10 mm to ensure a perfect final fit. In the summer of 2001, the structure was then dismantled and transported on 35 lorries to Falkirk, before all being bolted back together again on the ground, and finally lifted into position in five large sections by crane. The Wheel would need to withstand immense and constantly changing stresses as it rotated, so to make the structure more robust, the steel sections were bolted rather than welded together. Over 45, 000 bolt holes were matched with their bolts, and each bolt was hand-tightened. JLr2j
The various parts of The Falkirk Wheel
were all constructed and assembled, like one giant toy building set, at Butterley Engineering's Steelworks in Derbyshire, some 400 km from Falkirk. A team there carefully assembled the 1, 200 tonnes of steel, painstakingly fitting the pieces together to an accuracy of just 10 mm to ensure a perfect final fit. In the summer of
2001, the structure was then dismantled and transported on 35 lorries to Falkirk, before all being bolted back together again on the ground, and finally lifted into
position in five large sections by crane. The Wheel would need to withstand immense and constantly changing stresses as it rotated, so to make the structure more robust, the steel sections were bolted rather than welded together. Over 45, 000 bolt holes were matched with their bolts,
and each bolt was hand-tightened.
The various parts of The
Falkirk
Wheel
were all constructed and assembled, like one giant toy building set, at
Butterley
Engineering's Steelworks in Derbyshire,
some
400 km from
Falkirk
. A team there
carefully
assembled the 1, 200 tonnes of steel,
painstakingly
fitting the pieces together to an accuracy of
just
10 mm to ensure a perfect final fit. In the summer of
2001, the structure was then dismantled and transported on 35 lorries to
Falkirk
,
before
all
being bolted
back together again on the ground, and
finally
lifted into
position in five large sections by crane. The Wheel would need to withstand immense and
constantly
changing
stresses
as it rotated,
so
to
make
the structure more robust, the steel sections
were bolted
rather
than welded together. Over 45, 000 bolt holes
were matched
with their bolts,
and each bolt was hand-tightened.